Project Manager's Contact Information
|
Mark Tiano
Project Manager, Region 8 Design, NYSDOT
845-431-5775
[email protected]
Timothy Nelson, EIC
Engineer-In-Charge
New York State Department of Transportation, Hudson Valley Region
(845) 688-3270 | c: (845) 476-5038
[email protected]
|
Project Status (Updated September 2020)
|
The New York State Department of Transportation (NYSDOT) hosted an open house on 6/19/19 at Kingston City Hall to present the preliminary plans for a section of the Empire State Trail. Open house presentation boards: Project Information, Typical Sections I, and Typical Sections II. Comments were received by Mr. Mark Tiano, PE, NYS Department of Transportation, 4 Burnett Boulevard, Poughkeepsie, NY 12603, [email protected] The comment period for design is now closed as design has been completed, and it is being constructed.
The final plans were completed, and the project was advertised for bid by the NYSDOT on November 15th, 2019. Construction began in the spring of 2020.
|