Roadwork update
Week of September 20
Preparation for paving on Navara Street and Linderman Avenue from Washington Avenue to Twin Ponds Drive will begin on Wednesday, September 22. Paving is scheduled to commence on September 29, 2021 and be completed by October 1, weather permitting. During this time, there may be detours and changes to the traffic pattern.
Broadway Streetscape: striping and painting is not yet complete, including the green paint which will form the bike lane. All traffic signals are not yet operational, and bike lane signals have not yet been installed. Once the bike lane signals are activated, the bike lane will open for cyclists.
Broadway/Grand Intersection: Prince Street will reopen on Monday, September 20, and Grand Street will close to through traffic. Grand Street will temporarily become a dead end with detours in place.
Week of August 30
Central Hudson: Gas service installations will continue on Lounsbury Place (between Mountainview Avenue and Johnston Avenue), Irving Court, and Grandview Ave (between Lounsbury Ct and Main St) with temporary road closures and detours.
Broadway Streetscape: this week, crews will be milling from Henry St. to YMCA and also from Roundabout to Restorative Justice Center on Monday and Tuesday. Then Wednesday to Friday, weather depending, paving is planned. Permanent striping will be done Friday night. The following week, the signal work will continue and other details, including installing the sensor discs in the pavement to align all signals for communication to each other.
Week of August 23
Paving: Abeel has been milled/prepped for paving, and will be paved on Thursday, August 26, weather depending, from Wilbur Ave to Hudson St. Expect delays with alternating lanes of traffic. Paving on Abeel St from Hudson St. to Ravine St. will follow in a few weeks.
Roundabout: final signage is being installed and should be completed by Friday, August 27. Small tree planting will begin Monday, August 23. Larger trees will be planted during the planting season which starts September 15.
Broadway Streetscape: Milling will begin this week from Henry Street to Pine Grove, and Broadway will then be fully paved from the Roundabout to Pine Grove Ave. Paving is expected to be completed by Thursday, September 2, weather depending.
Central Hudson: Gas service installations will continue on Pearl Street (between Johnston Avenue and Valentine Avenue), Valentine Ave (between Pearl St and Valentine Ct), Lounsbury Pl (between Mountainview Ave and Johnston Ave), and Irving Ct with temporary road closures and detours.
Week of August 16
Broadway Streetscape: crews are milling as needed in the area of the sewer project (from the Restorative Justice Center to Henry Street). Paving should be completed in this area by Friday, August 20, weather depending.
Milling will begin next week from Henry Street to Pine Grove, and will then be fully paved from the Roundabout to Pine Grove Ave. Paving is expected to be completed by Thursday, September 2, weather depending. Electrical work to remove old signals and power new signage will occur next week.
Broadway/Grand Intersection Improvement: The outline of the new intersection has been rough graded, curbing is being installed and drainage structure have been installed. Poles bases will be poured next week.
Roundabout: final signage is being installed and should be completed by Friday, August 27. Small tree planting will begin Monday, August 23. Larger trees will be planted during the planting season which starts September 15.
Elmendorf Bridge: Construction has begun, with official detours in place. The
bridge and trail underneath have been fenced off. Demolition has started with asbestos removal from
the structure.
Central Hudson: Gas service installations
will continue on Pearl Street between Johnston
Avenue and Valentine Avenue with temporary road closures and detours, Valentine
Ave between Pearl St and Valentine Ct, and Lounsbury Pl between
Mountainview Ave and Johnston Ave.
Week of August 9
Broadway Streetscape: last vault work is nearing completion. Finishing
touches being completed on pavers and sidewalks as soon as vaults are done. Signals
are being prepared for energizing. Trees and plantings were delayed due to the
heat wave and will be planted Friday, August 13. Milling and paving is
expected to start Monday, August 16 and is expected to be completed by Labor
Day.
Broadway/Grand Street Intersection: drainage has been
installed. Concrete bases for lightpoles expected to be installed on Friday. (Photo below)
Central Hudson: Gas main installation will continue on Rogers Street (between Broadway and Wurts Street) with temporary road closures and detours.
Gas main installation will continue on Pearl St (between Johnston Ave and Valentine Ave), Valentine Ave, Patriots Pl, Grandview Ave (between Lounsbury Ct and Main St), Lounsbury Pl (between Johnston Ave and Grandview Ave), and Main St (between Washington Ave and Emerson St).
Gas service installations will continue on Mountainview Ave (between Main Street and Pearl Street) and Pearl Street (between Johnston Avenue and Valentine Avenue) with temporary road closures and detours.
Work progressing at Broadway/Grand St.
Week of August 2
Paving: Hunter Street
from Wurts to Ravine and McEntee Street from Broadway to West Pierpont will be milled on or about August 2, weather depending. Paving
is scheduled to begin on August 9, 2021. Paving is
expected to be completed by August 13, weather permitting. There will be
intermittent lane changes and detours, which may cause slight delays.
I-587 Roundabout: construction work is nearing completion. Night work will occur the week of August 2 to complete paving. During this time, the roundabout will be closed to traffic and detours will be put into place. Once paving is complete, final
striping will begin along with road sign installations. Plantings will take place in September in fall planting season.
Central Hudson: Gas main installation will continue the week of 8/2 on Hone Street (between Mcentee Street and W. Pierpont St) Mcentee Street (between Wurts Street and Hone Street), Russell Street (between Spring Street and W Pierpont Street), Ravine Street (between W Pierpont Street and Spring Street), Spring Street (between Hone Street and Russell Street) and Rogers Street (between Broadway and Wurts Street) with temporary road closures and detours.
Gas service installations will continue the week of 8/2 on Mcentee Street
Gas service installations will continue the week of 8/2 on Mountainview Ave (between Main Street and Pearl Street) and Pearl Street (between Johnston Avenue and Valentine Avenue) with temporary road closures and detours.
Week of July 26
Paving: NYS DOT will be paving Washington Ave from Hurley Ave to the bridge over Esopus Creek next week. DOT began milling on Washington Ave in preparation of paving, which is tentatively scheduled for the nights of July 28-29. Detours will be put into place during paving.
Broadway Streetscape: curb installation is nearly complete, and sidewalk installation continues.
Broadway Sewer work is complete except for final re-paving and adjustments of manholes or replacement of existing lids. Paving will start after all sidewalks are installed.
Broadway/Grand Street Intersection: preparation for this project has begun, with some overhead electrical wiring and other utilities are being removed. Construction work will start this week, weather depending. Prince Street will be closed starting Monday, July 26.
I-587 Roundabout: construction work is nearing completion. Night work will occur the week of August 2 to complete paving. During this time, the roundabout will be closed to traffic and detours will be put into place
Central Hudson: Gas
main installation will continue on Lounsbury Place (between
Johnston Avenue and Grandview Avenue), Main St (between Washington Ave
and Emerson St), Grandview Avenue (between Lounsbury Court and Main
Street), and Pearl St (between Johnston Ave and Valentine Ave) with
temporary road closures and detours.
Gas
main installation will continue on Hone St (between
Mcentee and Spring St), Mcentee Street (between Wurts Street and Hone
Street), Russel St (Between Spring St and W. Pierpont St), Ravine St
(between W. Pierpont St and Spring St), Spring St (between Hone St
and Russel St), and Rogers St (between Broadway and Wurts St) with
temporary road closures and detours.
Gas
service installations will continue on Spring
Street, Mcentee Street, Hone Street, Ravine St and W. Pierpont Street
with temporary road closures and detours. Gas service installations
will continue on Mountainview Ave (between Main
Street and Pearl Street) and Pearl Street (between Johnston Avenue and
Valentine Avenue) with temporary road closures and detours.
Week of July 19
Paving: Paving on Gill Street, Catherine Street, and East Strand has now been completed.
NYS DOT will be paving Washington Ave from Hurley Ave to the bridge over Esopus Creek. DOT will be milling on Washington Ave starting Wednesday (tomorrow) night from 7:00pm to 6:00am and Thursday, July 22 from 7:00pm to 6:00am. Paving is tentatively scheduled for the nights of 7/28 and 7/29.
Broadway Streetscape: curb installation is nearly complete. Sidewalk pour planned for Wednesday with one more pour after that will complete all sidewalk except for one or two small spots for signal work.
Broadway Sewer work is complete except for paving and adjustments of manholes or replacement of existing lids. Paving will start after all sidewalk pours are done.
Broadway/Grand Street Intersection overhead electrical wiring and other utilities being removed, with some electrical re-aligned to allow work to go forward. Drainage structures are due to arrive Thursday which will allow work to start in earnest, scheduled for Monday. Prince Street will be closed starting July 26.
Central Hudson: Gas main installation will continue this week on Lounsbury Place (between Johnston Avenue and Grandview Avenue), Irving Place, and Grandview Ave (between Lounsbury Ct and Main St) with temporary road closures and detours.
Gas main installation will continue on Mcentee Street (between Wurts Street and Hone Street) with temporary road closures and detours.
Gas service installations will continue on Spring Street, Mcentee Street, Hone Street and W. Pierpont Street with temporary road closures and detours.
Gas service installations will continue on Mountainview Ave (between Main St and Pearl St) and Pearl St (between Johnston Ave and Valentine Ave) with temporary road closures and detours.
I-587 Roundabout: night paving work is currently planned for the week of July 26, which will close the intersection from 8:00PM to 6:00AM for two nights. Detours will be put in place when the roundabout is closed, and the intersection will be reopened each morning. Additional night work will take place the week of 7/26/21 but traffic will be maintained onsite.
7/26/21 – night work maintaining traffic
7/27/21 – roundabout closed from 8pm-6am with detours in place
7/28/21 - roundabout closed from 8pm-6am with detours in place
7/29/21 – night work maintaining traffic
New Paving on Gill St.
Week of July 12
Broadway Streetscape continues with curb installations this week. All curbs should be installed by the end of the week. Sidewalk installation continues and is also expected to be completed soon. Signal installation is ongoing. Last vault installation planned for next week.
Broadway Sewer work is complete except for street reconstruction. Base paving is done with next layer of binder scheduled for next week as all curb will be in.
Broadway/Grand Intersection: work has started on a limited basis at Grand Street.
Central Hudson: Gas main installation will continue on Pearl St (between Mountainview Ave and Valentine Ave), Valentine Ave, Lounsbury Pl (between Johnston Ave and Grandview Ave), and Irving Pl. with temporary road closures and detours.
Gas main installation will continue on Mcentee St (between Wurts St and Hone St) with temporary road closures and detours.
Gas service installations will continue this week on Hone St, W. Pierpont St, Mcentee St, and Spring St with temporary road closures and detours.
Week of July 5
Paving: milling operations will begin
on or about Tuesday, July 6 and paving is scheduled to start on Monday, July 12
and be completed by Friday, July 16, 2021, weather depending on the following streets: Gill Street (from Yeoman to E. Strand), Catherine St (from Gill to Sycamore) and E. Strand from Abruyn to the trolley tracks. There will be
intermittent lane changes and detours, which may cause slight delays.
Broadway sewer: the new sewer pipe is installed and connected. Crews are currently adjusting the various manholes tops to fit the new reconstruction of the road. The reconstruction of the road is not complete as the paving on the south side was delayed due to rain last week. The second layer of asphalt (called binder) over all road reconstruction is scheduled for the week of July 19. The final layer of asphalt (called top) will be coordinated with Streetscape project and is expected to be occur in early August.
Broadway Streetscape is moving forward with curb and sidewalk installations. There have been interruptions due to finding abandoned fuel oil tanks under the sidewalk area. Those have been remediated per DEC regulations. Plantings are in and being watered. Signal poles and pedestrian poles continue to be wired up as soon as possible. Wrappings and other signage is due to be installed soon.
Paving for both Broadway projects will be complete by Labor Day weekend.
Broadway/Grand Street intersection work is starting up. Test pits to confirm utility locations have been done and contractor has ordered the required drainage structures. Signage and other maintenance protection of traffic (MPT) items will be set up this week.
Central Hudson: crews continue with main installation on the Southwest Kingston DIP through the end of this week and next week. Work will continue on Pearl St and Valentine Ave with road closures and detours. Main installation will move next week to Lounsbury Pl once main has been installed on Pearl St and Valentine Ave.
J Mullen will continue with service replacements on the lower Broadway project on the following streets:
Hone St (between Spring and Mcentee) – with road closures and detours
W. Pierpont St (between Hone and Ravine) – with road closures and detours
Spring St (between Hone and Russell) with road closures and detours
Week of June 28
Broadway Streetscape: work continues with prepping and installing underdrain, bioswales, sidewalk and curb. Also will be working on basement entrances that are being upgraded.
Broadway Sewer: continue with removing pavement, installing subbase, and paving along the south side of Broadway. Lining of the existing storm sewer planned for Tuesday, June 29.
Central Hudson: Starting Friday, June 25, work will begin on Mountainview Ave at the intersection of Main St.
Gas main installation will continue the week of June 28 on:
McEntee St – (between Wurts and W. Pierpont) with street closures and detours
Rogers St – (between Broadway and Wurts) with street closures and detours
Spring St – (between Russell and Hone) with road closures and detours
W. Pierpont – (between Wurts and Montrepose) with road closures and detours
Russell St – (between Spring and W. Pierpont) with road closures and detours
Ravine St – (between W. Pierpont and Spring) with road closures and detours
Gas service installations will continue the week of June 28 on:
Spring Street (between Wurts and Russell) with road closures and detours.
Wurts Street (between McEntee and Adams) with road closures and detours.
Presidents Place with road closures and detours.
Hone Street (between McEntee and Spring) with road closures and detours.
W. Pierpont Street (between Hone and Ravine) with road closures and detours.
Week of June 21
Midtown Linear Park: work on the Midtown Linear Park trail will be working on Cornell Street crossing on Tuesday, June 22 and Wednesday, June 23 and then will move to O'Neil Street on Thursday, June 24 and Friday, June 25. There will be flaggers for traffic control with lane closures throughout the day.
Broadway Streetscape: this week, installation of bioswales continues, along with grading for sidewalks and curb installation. Drainage structures will also be installed/adjusted.
Broadway Sewer: road reconstruction on the south side of Broadway has begun including, removing existing material, grading and installing sub base. This work will intermittently interrupt Franklin, Liberty, Van Deusen St. entry and exit. Then paving will begin and will likely go into next week. Lining of the existing storm sewer tentatively scheduled for next week.
Central Hudson: Gas main installation will continue this week on Wurts St. (between McEntee and W. Pierpont), W. Pierpont St. (between Ravine and Hone), Rogers St (intersection of Wurts), McEntee St (between Wurts and W. Pierpont), Hone St (between Mcentee and Spring), Russel St (intersection of W. Pierpont), and Ravine St (between Spring and W. Pierpont).
Gas service installations will continue on Spring St, Wurts St, Presidents Pl, Hone St, and W. Pierpont Street. When crews are actively working on these streets, please expect road closures and detours.
Week of June 7
Paving: Pearl Street from Clinton Avenue to Johnston Avenue has been milled and prepared for paving, which will start on June 7, weather depending.
Broadway Sewer: Van Deusen Street will be closed between Delmont Place and Broadway from Monday, June 7 through Friday, June 11. Please seek alternate routes.
Central Hudson: Gas main installation will continue the week of June 7 on Spring St, Hone Street, Presidents Place, W. Union Street, and W. Pierpont Street. Gas service installations will continue on Spring St, W. Union St, and Wurts Street.
I-587 Roundabout: The curb islands will be graded and prepared for the placement of stamped concrete beginning on June 7. During the week of June 7, the remaining concrete sidewalks will be completed. Installation of the blue stone sidewalks on Albany Avenue is scheduled to begin the week of June 14. Excavations, the placement of special planting mix and the plantings will begin the week of June 7. Additionally, full depth pavement along I-587 and Rent-A-Center will take place with the continuation of the installation of highway street lighting. Expect minor delays.
Week of May 31
I-587 Roundabout: The curb islands will be graded and prepared for the placement of stamped concrete beginning on June 3. During the week of June 7, the remaining concrete sidewalks will be completed. Installation of the blue stone sidewalks on Albany Avenue is awaiting confirmation from the quarry. Excavations, the placement of special planting mix and the plantings will begin the week of June 7. Additionally, full depth pavement along I-587 and Rent-A-Center will take place with the continuation of the installation of highway street lighting. Expect minor delays.
Central Hudson: Gas main installation will continue the week of June 1 on Spring St, McEntee Street, Hone Street, and W. Pierpont St. Gas service installations will continue on Abeel Street, Spring Street, and Wurts Street.
Broadway Streetscape: Ongoing paver installations along the north side. Contractor continues with sidewalk and curb grading including bioswale installation. Additional plantings and watering are scheduled this week.
Broadway Sewer: Work continues on connecting laterals including removing old lead water lines. Reconstruction of the south side should start block by block this week. Traffic patterns during the work hours will shift back and forth as work is being done on both sides of the road. Liberty from Broadway to Prospect Street will be closed on Friday.
Week of May 24
I-587 Roundabout: The remaining curb islands will be installed the week of 5/24. During the week of June 1, stamped concrete will be poured, excavations and beginning plantings will begin. Additionally, full depth pavement along I-587 and Rent-A-Center will take place with the continuation of the installation of highway street lighting. Expect minor delays.
Motorists are urged to slow down and drive responsibly in work zones. Fines are doubled for speeding in a work zone. Convictions of two or more speeding violations in a work zone could result in the suspension of an individual’s driver license.
Broadway Streetscape: Last week, the first trees and shrubs on the south side from YMCA to UPAC were planted. Sidewalk prep and installation continues this week. Four more lightpole bases will be installed as well as amenities: bench, trash, recycling containers, and bike stands.
Broadway Sewer: Sewer work continues. The Elmendorf to Broadway connection done has been completed. This week, street reconstruction will continue on the north side including more paving.
Central Hudson: Gas main installation will continue the week of May 24 on Hunter St, Hone St, W. Union St, and Abeel St. with detours and temporary road closures. Gas main installation will begin the week of May 24 on Wurts St and McEntee St. with detours and temporary road closures. Service work will continue on Abeel St and Rogers St.
Beginning in June, the project area will move. Construction is expected to take 10 weeks. Construction trenching will occur along:
- Lounsbury Pl, between Grandview Ave and Johnston Ave
- Lounsbury Ct
- Grandview Ave, between Lounsbury Pl and Main St
- Mountain View Ave, between Main St and Pearl St
- Pearl St, between Valentine Ave and Johnston Ave
- Valentine Ave, between Pearl St and Valentine Ct
- Irving Pl
- Main St, between Emerson St and Washington Ave
Week of May 17
Central Hudson: Main Installation will continue week on W. Union St and Abeel St with road closures and detours. Service installations to continue on W. Union Street. Work to tie in new gas main and retire existing gas mains will be occurring on: Ravine St, Hunter St, German St, Ridge St, and Hone St. Road closures and detours should be expected.
Broadway Sewer: preparing the new base of asphalt between Down and Elmendorf Monday for paving starting Tuesday. Elmendorf will be closed Wednesday for a few days with access through the parking lot off Broadway for the tenants of Elmendorf.
Broadway Streetscape: continuing to install sidewalk on the north side. Remaining light poles will be installed and connected. Plants for the south bioswales will be delivered Wednesday and planting starting Thursday.
Week of May 10, 2021
Central Hudson: Main installation will continue on W. Union St and Abeel St with lane closures and detours. Main tie-in work will also take place on Ravine, German, and Ridge Streets.
Service replacements will continue on Hunter St, W. Union St, and Hone St
Broadway Sewer: crews are 30’ away from tying in the new sewer line to the existing active sewer manhole at the west end of the job. Once all connections are done and line is completely tested it will go active, likely in the next two weeks. Road reconstruction will begin once sewer work is completed.
Broadway Streetscape: work continues with curb installation and prepping for sidewalk placement possibly next week. Bioswales being installed and some plantings of trees on the south side may start next week. The final lightpoles on the west end were erected. Vaults into the basements are moving forward.
I-587 Roundabout: Re-configuration of the intersection at I587, Albany Avenue and Broadway will commence the night of Monday, May 10. Project will be moved to Phase 5 configuration (Roundabout) for Tuesday, May 11. Place Work Zone Traffic Control for one evening of night work on May 10. Stripe for Phase 5 re-configuration (Roundabout) and remove traffic signals. In addition, installation of highway street lighting will continue through the week of 5/10. Expect minor delays.
Week of May 3, 2021
Central Hudson: Gas main installation will continue on W. Union St between Wurts and Broadway, and on Abeel St between Broadway and Wurts. Service replacements will continue on Ravine St, German St, Hunter St, Hone St and W. Union St.
I-587 Roundabout: Re-configuration
of the intersection at I587, Albany Avenue and Broadway has been delayed due to
forecasted rain. Project
will tentatively be moved to Phase 5 configuration (Roundabout) on Monday, May 10, weather permitting. Place Work Zone Traffic Control for one evening of Night
Work on May 10. Stripe for Phase 5 re-configuration (Roundabout) and remove
traffic signals. In addition, installation of highway street lighting
will continue through the week of 5/10. Expect minor delays.
Broadway Streetscape: new curb in between Thomas and Cornell. Area being prepped by Anchor bar including connecting to 1-587 Roundabout. Installed pole bases with more on Monday.
Broadway Sewer Project: Preparing to install manhole on east side of Elmendorf to connect installed pipe. Installing laterals as we go along.
Paving will be occurring this week on Merilina Ave, Boulder Ave and Plymouth Ave.
Week of April 26, 2021
Central Hudson: Service replacements will continue on W. Pierpont St, Hudson St, Ravine St, German St, Ridge St, and Hunter St. Gas main installation to continue next week. Update: Gas main installation will continue sooner than expected on
Hone St and W Union St. J Mullen crews will be working on these streets through
the end of the week.
Broadway Sewer project: Last week, pavement was laid between O’Neil and Down on the north side. This week, connection continues for the sewer lateral, then grading, and paving (weather permitting).
Broadway Streetscape: Work continues this week with vaults and bioswales, underdrain, curb, sidewalk prep near Anchor bar and Optician areas. Curb scheduled for next week, then sidewalk. Will move into other areas as sewer work wraps up. Light and signal pole bases being done.
I-587 Roundabout: Excavation for
sidewalk continues throughout the project. Fine grading on Albany Avenue
in preparation for paving which will begin on Friday, April 30. Place Work Zone
Traffic Control for one evening of night work on May 5. Stripe for Phase 5
re-configuration and remove traffic signals. Project will
be in Phase 5 configuration (Roundabout) on May 6. In addition, installation
of highway street lighting will continue through the week of April 26. Expect
minor delays.
Week of April 19, 2021
Central Hudson: Main installation to continue on German Street, Hunter Street, W. Union Street, Hone Street, and Abeel Street with lane closures and detours. Service installations to continue on Hudson Street, W. Pierpont Street, Spruce Street, Ravine Street, German Street, and Ridge Street with road closures and detours.
Broadway Streetscape: walls have been poured for the first two vaults at 580 and 582 Broadway. The sidewalks in the area of Thomas to Cornell have been removed and grading is ongoing. The vault at 618 is excavated, and numerous light pole bases and crossings have been done. The area by 744 Broadway east has had sidewalk removed and rough grading for curb has been done. Expect tentatively curb in about two weeks, then sidewalks, then pavers as work progresses. Light poles and conduit also.
Broadway Sewer: the directional boring under Elmendorf was accomplished. Trenching and pipe placement continues toward Elmendorf. The laterals for sewer are being installed as are the copper waterlines. Next week A. Colarusso & Son will begin the rebuilding of the north side of Broadway from O’Neil heading west. New subbase to start along with asphalt base and binder eventually will be placed.
Week of April 12, 2021
I-587 Roundabout: Fine grading for new highway sections and curb on Albany Avenue, I-587 and throughout the project limits will continue through the week. Highway drainage installation continues through the week. In addition, installation of highway street lighting will continue through the week. Excavation for sidewalk will begin on April 19. Expect minor delays.
Central Hudson: For the week of April 12, J Mullen will be starting gas main installation on Hunter St in its entirety, Hone St and W. Union St, and then moving to German St. A service replacement crew is working on W. Pierpont/Hudson St and will continue there through at least the end of the week.
Week of April 5, 2021
J Mullen will continue installing gas main on Spruce St and expects to complete work early in the week. Upon completion of Spruce St, the entire section of W. Pierpont from Montrepose Ave to the end of Hudson St including Spruce St will have gas main installed. Service replacements are expected to begin later this week on W. Pierpont and Hudson St.
After the gas main is installed on Spruce St, a crew will begin installing gas main on Ravine St between Hunter St and German St. They will continue down German St and onto Ridge St from there.
Starting Monday, CSX will be working on three crossings for approximately 3-5 days. The following roads will be closed: Foxhall Avenue, Ten Broeck Avenue, and Smith Ave.
Week of March 29
UPDATE: Tremper Ave between Albany Ave and Elmendorf Street will be closed Thursday, April 1 for repair work.
I-587 Roundabout: Excavation for new highway sections on Albany Avenue will continue the week of March 29. Highway drainage installation will commence on Monday, March 29 throughout the project limits. In addition, installation of highway street lighting will continue through the week. Expect minor delays. The work as listed above is subject to change based upon weather and possible supply issues.
Central Hudson: Last week Central Hudson successfully installed 1145’ of 6”pipe starting from the intersection of W. Pierpont St and Montrepose Ave and continuing down Hudson St to just before the Abeel St intersection.
Starting later this week, J Mullen will briefly leave the area of Hudson Street to focus on installing main and services on Rogers Street, in the vicinity of the Kingston Catholic School, due to the school being on spring break when there will be less impact to the school’s daily operation. After the main is installed on Rogers Street, a crew will then return to installing main on Hudson St and Spruce St, while a service replacement crew works on completing service swaps on Rogers St.
Next week, starting on/around April 8 CSX will be working on three crossings for approximately 3-5 days. The following roads will be closed: Foxhall Avenue, Ten Broeck Avenue, and Smith Ave.
Week of March 22
Downs Street will be closed off from Broadway starting Thursday, March 25, for the installation of new sewer lines across the intersection, and is expected to be closed for 1-2 weeks.
The public parking lot will be accessible from Downs street during this intersection closure. Parking for Sea Deli, Masa Midtown and other nearby Broadway businesses will be available at the Downs Street municipal lot and will be accessible by foot.
Central Hudson is working with J. Mullen & Sons to install new natural gas distribution mains and services. Replacement of approximately 10,600 feet of gas lines in the City of Kingston is formally set to begin on March 23 and the project is estimated to take 5 months to complete.
Construction trenching will occur along:
• Rogers St, between Broadway and Adams St
• Wurts St, between McEntee St and W Pierpont St
• Wurts St, between Springs St and Hunter St
• McEntee St, between Wurts St and Ravine St
• W Pierpont St, between Hone St and Hudson St
• Hone St, between W Pierpont St and Spring St
• Hone St, between Hunter St and Abeel St
• Ravine St, between W Pierpont St and Spring St
• Ravine St, between German St and Hunter St
• Hudson St
• Spruce St
• Spring St, between Wurts St and Russell St
• Presidents Pl
• German St
• Hunter St, between Wurts St and Ravine St
• W Union St
• Abeel St, between Broadway and Wurts St
More info at https://kingston-ny.gov/filestorage/8463/13525/CH_gasline_lower-broadway.pdf